East End Trails

What do you think?

   June 2013

Laura Bailey Trail extented north across Eastview Rd. and through Eastview Sports Park

   September 2013

East-side trail loop extended south from Grange/Watson Rd. to Watson Parkway

   June 2010

Funds for the East-side "Laura Bailey Trail" to come from Carbon Tax Credits at the Eastview Landfill Gas Project. Trail location being finalized

   April 2010

Official Plan amendment made and East-side Trail loop included. A trail is now in the Official Plan that would connect the Eramosa River Trail to Guelph Lake

   April 2009

The board walk over Hadati Wetland was completed and the trail connection from

East End Trail reaching Eastview Rd.

October   2008

The bridge was installed over Hadati Creek just east of Summit View Drive

 

October  2007

The first half of the East end Trail network is completed, construction on the second half will begin in  2008

 

$870,000 of funding for East End trails has be approved in 2007

December 2006

Park design in progress with two public meeting held. Construction to begin next year

This is the current building plan

For more info call Jyoti Phathak, Trail Planner at the City

Phone: (519) 837-5616 Ext. 2431